Building Permits Explained: Documents, Plan Review, Inspections
A building permit is written permission from your local building department to carry out construction work, issued after the department has checked that the planned work follows the codes it has adopted. The permit is followed by inspections during construction, so the department can confirm that what was built matches what was approved. The details vary by city, county, state and country, but the shape of the process is broadly similar in most places.
When a permit is usually needed
Requirements are set locally, so always ask your building department. In general, permits are required for:
- new buildings, additions and accessory buildings above a locally set size;
- structural work: removing or altering walls, beams, columns, joists, rafters, trusses or foundations;
- electrical, plumbing, gas and mechanical (heating, cooling, ventilation) work beyond minor repairs;
- re-roofing and re-cladding in many places, and window and door replacements that change openings;
- decks, retaining walls, pools and fences above locally set heights;
- demolition;
- changes of use, such as converting a garage, basement or attic into living space, or a house into a business.
Cosmetic work such as painting, flooring and like-for-like minor repairs is often exempt, but the exemptions differ from place to place and do not exempt you from following the code. Never assume a wall is not load-bearing: structural changes are assessed by a licensed structural engineer or architect first.
Other approvals you may need
A building permit covers the building codes. Other rules usually need separate approval, sometimes before the building permit can be issued:
- Zoning: land use, setbacks, height, lot coverage and parking. A variance may be needed if a design does not fit.
- Historic district or landmark review for exterior changes to designated buildings or areas.
- Homeowner association or deed restrictions, which are private rules enforced separately.
- Floodplain, stormwater, tree and environmental permits, and permits for work in the public right-of-way (a driveway cut, a sewer connection).
The documents a typical application includes
| Document | What it shows |
|---|---|
| Application form | Owner, address, scope of work, contractor, estimated value of work |
| Site plan | Property lines, existing and new buildings, setbacks, driveways, utilities, drainage |
| Floor plans | Room layout, dimensions, doors and windows, room uses |
| Elevations and sections | Exterior appearance and heights; how the building is put together from foundation to roof |
| Structural drawings and calculations | Foundations, framing, beams and connections, often sealed by an engineer or architect |
| Energy compliance documentation | How insulation, windows, air sealing and equipment meet the adopted energy code |
| Mechanical, electrical and plumbing information | Systems layout and equipment, more detailed on larger projects |
| Other reports as required | Survey, soils (geotechnical) report, stormwater calculations, truss drawings, fire protection |
Whether the drawings must be sealed by a licensed architect or engineer depends on the project and local law; see when plans need a stamp. Many departments publish checklists of what they need for common projects, and many now accept applications and drawings electronically.
Plan review
Reviewers check the drawings against the adopted codes and local amendments (see how building codes work). It is normal to receive comments asking for corrections or more information. Your architect, engineer or contractor revises the drawings and resubmits until the department is satisfied. Incomplete applications are the most common cause of delay, so check the department's checklist before you submit. Once approved, the permit is issued, fees are paid, and the permit card is usually posted at the site.
Inspections
Inspections happen at stages when the work can still be seen. A typical sequence for a house or addition:
- Footing or foundation, before concrete is placed.
- Framing, once the structure is up.
- Rough-in electrical, plumbing and mechanical work, before walls are closed.
- Insulation and air sealing, where the energy code requires it.
- Final inspection when the work is complete.
Work should not be covered until it has passed the relevant inspection, or it may have to be opened up. Your contractor usually schedules inspections, but as the owner it is worth confirming each one was passed.
Certificate of occupancy
For new buildings, additions and changes of use, the department issues a certificate of occupancy (or a final approval) after the final inspection, confirming the building can be used for its approved purpose. Keep it with your permit records; lenders, insurers and future buyers may ask for it.
Who applies
Licensed contractors commonly pull permits for their own work. Many places allow owners to obtain permits for work on their own home, sometimes with conditions, and some trades (often electrical and gas) may be restricted to licensed professionals. Whoever holds the permit is responsible for the work meeting it, so be wary of anyone who asks you to pull a permit for work they will do.
Why skipping the permit is a bad idea
- No independent check that the structure, wiring, gas or fire separations are safe.
- Stop-work orders and penalties, and possibly having to open or remove finished work.
- Problems with insurance claims and when you sell or refinance, since buyers and lenders may check permit records.
Practical tips
- Call or visit the building department early with a description of the project and ask what it requires.
- Build plan review and inspection time into your schedule and budget; permit fees are often based on the project's value or size. The building cost estimator gives a rough construction figure for planning, not a quote.
- Keep copies of approved drawings, permits, inspection records and the certificate of occupancy.
- In older buildings, plan for testing before demolition: paint in US homes built before 1978 may contain lead (contractors paid to disturb it must be EPA lead-safe certified), and older materials may contain asbestos, which should be tested by an accredited professional before it is disturbed. Other countries have their own rules.
This article explains how building permits generally work and is not legal or professional advice. Requirements differ by location; confirm them with your local building department before work starts, and make decisions for a specific project with a licensed architect or engineer. Whether work complies is decided by the building official on plan review and inspection.